RSD Bond Updates

Posted Date: 07/02/26 (11:12 AM)


A red apple logo

RSD Bond Updates

Thanks to the community's support of the 2025 bond, construction crews are hard at work this summer making important improvements across Redmond School District schools.

From modernizing aging building systems and improving school safety to adding air conditioning, replacing roofs, upgrading athletic facilities, and creating better learning spaces, these projects are investments that will benefit students, staff, and our community for years to come.

Many of these projects will be completed before students return this fall, while larger projects at Redmond High School and Tumalo Community School will continue into 2027. Here's a look at what's happening across the district.
 

Redmond High School

Campus Modernization
One of the district's largest bond projects is underway at Redmond High School. This multi-year modernization includes replacing aging heating and cooling infrastructure, upgrading fire sprinkler and alarm systems, replacing the roof, remodeling the theater, Career and Technical Education (CTE) classrooms, commons, new wrestling addition, and locker rooms, installing new LED lighting throughout the building, and updating HVAC controls.

Many of these improvements replace systems that have reached the end of their useful life. For example, aging hydronic piping has caused frequent leaks and reduced the efficiency of the school's heating system. Replacing these systems will improve reliability, and reduce maintenance needs. 
Estimated completion: August 2027

New Visitor Football Bleachers
New elevated visitor bleachers are being installed at the football stadium, providing increased seating capacity and improved sightlines for spectators.
Estimated completion: July 2026

Turf Baseball and Softball Infields
The varsity baseball and softball infields are being converted to turf, creating more playable fields while reducing water use and ongoing maintenance.
Estimated completion: August 2026

No Access To Inside Redmond High School

For the safety of our community and construction crews, there is no public or staff access to Redmond High School during construction this summer.

If you need to access the Redmond High athletic fields, please park at the Jaqua Sports Complex or along SW 23rd Street and walk to the fields.

Please do not park in the front parking lot at the school, as it is an active construction zone. Also, please do not park in the bus lane at any time.

Thank you for your patience and cooperation as work continues to improve Redmond High School.
A construction site with a yellow excavator, blue pipes, and a 'Danger: Construction' sign behind a chain-link fence.
 

Sage Elementary

Cooling Improvements
A new chiller system is being installed to provide air conditioning to the school's second floor, improving comfort for students and staff during warmer months.
Estimated completion: August 2026

Construction workers in orange shirts and hard hats move wheelbarrows near a brick building.
 

Terrebonne Community School

Cooling Improvements
A new chiller system will provide air conditioning to the school's second floor, helping create a more comfortable learning environment.
Estimated completion: August 2026

Construction site with a building featuring red siding and a stone base, under a clear blue sky.
 

Hugh Hartman Elementary

Roof Replacement
The original roof, installed when the school opened in 1995, is being replaced to help protect the building for years to come.
Estimated completion: August 2026

A yellow telehandler with a dumpster is parked next to a building undergoing roof repairs.
 

Ridgeview High School

Secure Entry Vestibule
A new controlled entry vestibule will be added to the main office, allowing staff to better manage visitors and enhance school security.
Estimated completion: August 2026

Tennis Court Replacement
The tennis courts are being completely replaced to correct long-standing cracking and drainage issues, creating a safer and higher quality playing surface.
Estimated completion: August 2026

New Visitor Football Bleachers
New elevated visitor bleachers will provide additional seating and improved viewing for fans.
Estimated completion: July 2026

Turf Baseball and Softball Infields
The varsity baseball and softball infields are being converted to turf, increasing playability while reducing water consumption and maintenance.
Estimated completion: August 2026

A construction site with a scissor lift, caution tape, and building materials.
Construction site with exposed ceiling infrastructure, scaffolding, and a vacuum cleaner.
Construction site with metal poles planted in the ground under a cloudy sky.
 

Tom McCall Elementary

Secure Entry Vestibule
Tom McCall will receive a new controlled entry vestibule, completing the district's efforts to provide enhanced visitor management and security at every school.
Estimated completion: August 2026

Construction framing is underway, with wooden studs forming new walls and doorways.
 

Obsidian Middle School

Interior Upgrades
Remaining restrooms not included in the 2022 renovation project are being modernized, including the addition of ADA-accessible stalls. The project also includes new energy-efficient LED lighting throughout the building. Flooring and other modernization will be enhanced.  
Estimated completion: August 2026

A hallway undergoing renovation with exposed ceiling infrastructure and debris on the floor.
A construction worker in a yellow shirt and hard hat uses a jackhammer on a dirt floor inside a room under renovation.
 
Workers in hard hats and safety vests are clearing debris from a room labeled 'Music'.
 

Tumalo Community School

School Modernization & Expansion
Tumalo Community School is receiving a major modernization that will allow the school to once again serve students in grades K-8. The project includes four new classrooms, expanded kitchen and cafeteria space, updated interior finishes, site improvements, new LED lighting throughout the building, and upgraded HVAC controls.
Estimated completion: August 2027

 
Construction workers in hard hats and safety vests oversee excavation near a building.
 

Transition Program Building

The district's Transitions Program is receiving a permanent home with the relocation of a building from Terrebonne to district property near SW 23rd Street. This project provides a dedicated space for the program, which has previously moved between buildings as enrollment and space needs changed.
Estimated completion: July 2026

A construction site with a building under construction, scaffolding, and freshly poured concrete sidewalk.
 

THANK YOU!

As work continues across the district, we thank our community for its continued support of the 2025 bond and its investment in Redmond School District students. These projects reflect a shared commitment to providing safe, modern, and efficient schools where students can learn, grow, and thrive for generations to come.

We'll continue sharing updates as projects progress and look forward to celebrating these improvements.
 